If you are a serious DIY-er, at some point in your journey, you will probably need to build a wall of some sort. To cover pipes, to create a divider in a room, or to add storage of some kind. Today, let’s look at the step-by-step guide for building a stud wall. In my case, I am building a stud wall in the bathroom to cover the bathroom pipes.
Until you go through the demolition, it is hard to know how much construction you might need to do. In my case, I removed a built-in vanity and wall that was hiding the waste pipe for the toilet and basin. I also removed a wall, covering pipework for the bath tub.

Removing the wall revealed an angled beam in the corner, which had been hidden. I love the look of the beam, and it goes with the same feature in other rooms of the house. So I was happy to discover this hidden structural element. It will be featured in the new design of the guest bath.

However, once we could see what we were working with, it became clear that we would need to find a way to cover the waste and water pipes on the left wall. I do not want to simply replace the vanity with the same thing. As well, the waste pipe cannot be easily moved, as it connects too many different fixtures in both baths. And as we live in a multi-flat building, it may also connect to other bathrooms throughout the building.

I could simply box in the pipe, but I have never liked this look. You know what is behind the box, and it just looks like a cheap solution to the challenge. Instead, I’m building a higher wall that will align to the height of the paneling in the rest of the room. This will close the room in a bit more. Especially considering that we used to have a huge wall mirror in the place where the new wall will be. But, I like the idea of how this could look, vs. a low counter like we previously had. Or a very short box just covering the waste pipe.
I have never built a wall before, so here’s to learning yet another new skill in this huge DIY effort.
A Wall To Cover Pipes and Create More Storage
If you’ve been following me for any length of time, you know that I am on the constant hunt for space and good storage solutions. The bathroom renovation is no exception. By building a stud wall, I will lose some valuable floor space, but I will make up for it. I plan on adding a recessed cupboard just above where the toilet will sit, so we will gain some closed storage. And this will make good use of the empty space behind the wall.
I also will construct a recessed cubbie in the shower for holding shampoo, soap and the like. So building a stud wall will lead to some useful storage, even if it does mean we lose a bit of floor space.
Let’s get started building a stud wall.
The Tools and Materials Needed
- C16 CLS timber
- Screws: I used 4.5 wood screws in a mix of 6 and 6.5mmm lengths
- Spirit level
- Wall anchors
- Mitre box or other saw
- Drill and screwdriver
The Process for Building a Stud Wall
The first step is taking good measurements and drawing out your plan.
In my case, I made several different drawings, trying different things to ensure the wall works in the space.
I originally wanted the wall to align to the steel beam we discovered during demolition, which put the depth of the wall at 17cm. This is a narrow wall, and honestly, it is slightly shy of one bend in the waste pipe in the back corner. I had hoped that with the addition of the wall board, we would be able to cover the pipe fully. I was doubtful but decided to try. After all, I want the wall to take up the least amount of room possible in an already small space.

After getting a rough frame in place, my plumber took one look and pointed out that it does not fully cover the waste pipe for the toilet. I was so focused on the back corner that I completely missed the toilet waste pipe right in front of me! The wall was short of covering the pipe by about 7cm. With plasterboard, I could cover some of the difference, but not enough.

I debated just bulking the original frame up with more wood. But in the end, I decided to take it down and start over. I was able to leave some of the framing I had screwed into the wall, but I dismantled most of it. While a bit discouraging, I am looking at it as just one more opportunity to practice my wall-building skills! #evertheoptimist
Stud Wall Redux
After lots more measurements, I landed on a depth of 26cm for the wall. This would just cover the waste pipe, and with plasterboard, I’m losing about 27cm of floor space.
As for height, this will be a high wall at 180cm. This is about two-thirds of the total room height. The plan is for the top of the wall to align with the top of the paneling on the other walls in the room. The top third of the wall above the paneling will be wallpapered.

I’ve re-drawn the plans with the new measurements. You can see where I’ve added in the hidden cupboard and the shower cubbie, to gain some more storage.

Map the Design on the Wall and Floor
This is where things start to get fun. Drawing on the walls and floor! Grab your marker or pencil, a tape measure and a spirit level, and start drawing the new wall design in real life.
This will give you a good sense of the final wall, and it will help guide the building of a stud wall. You can adjust as needed, once you see your plan on the big screen, so to speak.

In my case, I drew out the frame of the wall on the existing wall, with the top at 180cm and the width at 178cm. (The wall will stop where the toilet waste pipe ends, and there will be a small cabinet to the left where the washing machine will sit. More on that another day.) I marked the depth of the new wall, 26cm, on the floor as well, this time making sure it is deep enough to cover the waste pipe.
It is important to think about the stud placement when building a stud wall. Especially if you are working around obstacles like pipework. You need to ensure you have surface area for hanging the wall boards or tile backer boards. As well, you want to follow local building codes. In general, in the UK, studs should be between 400mm and 600mm, although it might vary depending on what you are hanging on the stud wall.
Part of my wall will be for the shower, with tile backer boards, tiling, and the shower enclosure. I want to ensure it is very strong and stable, to withstand the weight.
And, I want to include several cut-outs in the wall, for the hidden cupboard and the shower cubbie. I need to add studs to accommodate these two additions in the wall build. I drew the placement for both on the wall , and it was a good thing I did, because the sizing was a bit small for the space. So, I was able adjust it in real time and get a bigger cupboard than originally planned.
Cut the Frame, Studs and Noggins
Once you have the design and measurements and are confident of the sizing, it is time to cut the wood and start building a stud wall.
Before cutting, let’s discuss the timber you need to have for building a stud wall. After reading a very good tutorial on the B&Q site, How to Build a Stud Partition Wall, I purchased C16 CLS timber, which is planed and ideal for internal stud work. I purchased 9 pieces in 3-metre lengths, and the purchase price and delivery fee were quite reasonable. (I did try to pick them up from the store but my car was too small, and they could not cut them to a smaller size at the B&Q.)
You also could consider building a stud wall out of metal studs, but I just do not find metal as easy to work with as wood.
For my first attempt, I had built the wall in situ, or in place. But due to all the pipes, I ran into lots of challenges working around the pipes. I had to cut the horizontal for the floor into a few strips that would work around the various pipes, and I needed to make a few cutouts with the jig saw to work around some of the pipes where I could.

For the wall redux, since it was slightly deeper, I could avoid some of the pipes on the floor and build a more standard wall frame. For this reason, I decided to build the frame outside of the room and then bring it in for installation. I felt this would give me a more precise result and give me more space to work.
I also decided to split the wall into two separate parts. 178cm is quite long, and I was not convinced I could get it back into the room once built. There is also a natural split in the wall, because the portion of the wall in the shower needs to be higher than the planned 180cm for the rest of the wall. This is to account for the shower head, riser and general wetness of the area, so the height will be 210cm. This area will be tiled, so it is quite separate from the rest of the wall. by not going all the way to the ceiling with this part of the wall, I can still have the angled beam partly exposed too.
Build the Outer Frame
I began with the left part of the wall, which sits behind the toilet and measures 98cm. I built out the four sides first. The bottom and top studs are cut at 98cm, and the two outer sides at 176cm (180 minus the 4cm thickness of the top and bottom studs).
I screwed these together, going straight through the two pieces, with two screws per board. I checked for square, since the wall needs to be plumb and level for tiling and plaster boarding.

With the frame in place, I next added three horizontal pieces, also called noggins, inside the frame. I placed one at 15 cm from the top, which will be the top of the recessed cubbie. The bottom of the cubbie sits at 35cm below that, giving me a nice amount of space for storing bathroom products behind the wall. I also added a third horizontal 15mm below the cubbie. I am considering a second cubbie here for loo role, but we will see. To make sure, I checked the height was correct for the loo roll, but even if I do not build this out, the horizontal gives extra stability to the wall.

Up next, I cut two long verticals to brace off of the bottom horizontal. I spaced these just by eyeing them, and then, once in place, I added a horizontal in the middle of the two. These pieces are for stability, and for screwing the wall boards in place.
I added a few more verticals, above the cubbie and on either side. For every join, I used two screws, going in straight through both pieces of wood where possible, or at an angle if needed.

Now, it was looking like a proper wall. I checked everything once more for square, and then I carried it into the room to test the placement.
It just barely fit over the waste pipe. I could probably stand to move the vertical stud over to the right slightly, but we will see.

I may add a few more vertical studs into the loo role shelf and a few more horizontals in the lower half, but overall, it feels quite secure.
Giving the Wall Some Depth
I’ve built the face of the wall, but it needs support for the depth as well. One approach would be to repeat the wall I just built and attach the two at the right depth. But this will be challenging with so many pipes in the way. Instead, I’ve decided to add blocks of wood to achieve 26cm at various points across the backside of the wall, which I’ll attach to the existing wall.

A Quick Pro Tip for Cutting Multiple Pieces Equally
I needed to cut about 16 strips of the wood to brace the wall and achieve the depth needed. The blocks needed to be 19cm (26cm depth minus 7cm for the width of the studs). To achieve quick and repeatable results, you can clamp a block of scrap wood in place on your mitre saw as a barrier at the exact measurement, and then with each cut, press the end of the wood strip against this block. Simple and consistent cuts that all measure the same.




Rinse and Repeat
With one portion of the wall under my tool belt, I moved on to the right side, which is higher by 30cm.
I followed the same process, building out the outer frame with two horizontals and two verticals. For this portion, I added two verticals, in the location where the shower cubbie will be. I added a vertical below the lower horizontal for further stability.

Because this wall goes under the angled ceiling, I brought it into the room to test the placement. As expected, I needed to adjust the right top corner to account for the angle. I marked where the ceiling angle met the new wall and, removing these pieces, cut them down and re-attached them.

I needed to do the same for the bottom right corner, where the waste pipe makes a slight bend to go behind the wall. A vertical brace in both places further reinforces the corners.

I added the blocks of wood for the depth to the left side of this portion of the wall. For the right side, I had already added some framing for the original attempt, and I had left this in place. It is a little shallow for the new depth, so I bulked it up with some blocks of wood, and then attached the new wall to these.

Ta-Dah! A New Wall
With both portions of the wall built, including the right depth, I attached everything to the wall behind and the existing wood framing from my first attempt. The wall is strong and secure, and it covers the pipes.

I will probably add a few more vertical and horizontal studs, especially to the right side, once the plumber has come and completed first fix. It is important to ensure a very strong base for installing the shower head and taps, as well as the shower enclosure, which can be quite heavy. I also need to ensure a good structure for installing the shower cubbie and hidden cubbie. To do this, I will build the hidden cubbie out of plywood, and I ordered a specially made shower cubbie from JackoBoard, to go with the tile backer board and ensure complete waterproofing.

Another skill under my tool belt, and more progress on the bathroom renovation. I am pleased, but I still have so much to do. Have you built a wall before? Any tips to add here?
Up next, building up the flooring to be ready for tiling. The keen eyed among you may have noticed a changing floor in these pictures. I have been working in parallel on the floor and the stud wall, to be ready for first fix.
I’ll be back next week with a complete look at all the steps for flooring. We are getting there!
Happy DIY-ing!